1.5 Review The completed questionnaire and supporting documentation received from the new sub-contractor/supplier is then to be reviewed by QHSE, Finance managers, legal/contracts assessor and CEO
Once each departmental review has taken place and if approved Form 13.DC010 is to be updated and signed by the relevant management representative.
Sub-contractors and key suppliers will be subject to a pre-qualification check of their safety performance by review of their safety programs, safety training documents and safety statistics. The following information will also be a consideration for approval
ISO 9001, ISO 14001, ISO 45001 or OHSAS certification Visit feedback from any management visits QHSE performance Results from any QHSE audits
When reviewing all new sub-contractors and supplier questionnaires, the relevant Manager in addition to the information provided within the relevant questionnaire, should be also be considering the following:
Are there any legal implications of using the supplier (international trade restrictions etc.)? Are there any HSE reasons for not using the supplier? Does the Sub-contractor/supplier hold the required insurances? Does the supplier's credit rating etc. present an acceptable level of risk? Are there any ethical reasons for not using the supplier? Are there any HSE reasons for not using the supplier? If deemed necessary, the Finance manager is to check over the companies accounts with Companies House. |
|